The more observant of our followers may have noticed that we didn't publish an update last week. This was because we spent the whole day working on infrastructure (new storage containers) and ground equipment (Bovril's sick tug), and repositioning the aircraft which we had previously moved to provide access for the container delivery.
This week we were able to continue with the No 3 engine inspection, and good progress was made. We removed the HP compressor top half casing and inspected the stator and rotor blading, rotor spacers, etc. Everything was found to be in very good order, and by the end of the day we had the casing back on and fully bolted up.
This is the top half casing showing the stators.....

..and the hole in the engine which it normally occupies.
Next week we will put back all the "dressing items" (external piping, bulkhead diaphragm, etc) and get ready to refit the engine in the aircraft.
I am also pleased to announce that Bovril's tug is now better ~ it's amazing what an overhaul of the ignition system will do for a poorly petrol engine.